Skip to content
Join our Newsletter

MTA Opens Two Modernized Elevators at Atlantic Avenue-Barclays

mta-elevators
Replacement elevator EL307 returned to service at Atlantic Av-Barclays Center on Thursday, Nov 19, 2026. (Marc A. Hermann / MTA)

Two modernized elevators have opened at the Atlantic Avenue-Barclays Center station complex in Downtown Brooklyn. 

The project was completed on budget and brings the MTA’s total number of elevator replacements in 2026 to 27, the second-highest annual total in the agency’s history.

One elevator connects the station mezzanine with the B and Q train platform.

“We're modernizing elevators faster than ever, all while expanding accessibility across the system,” said MTA Construction and Development President Jamie Torres-Springer. “The Atlantic Avenue-Barclays Center station complex is a major transit hub for thousands of daily riders who can now count on more reliable elevator service for years to come.”

The other links the mezzanine with the Manhattan-bound 2 and 3 train platform. The complex serves more than 30,000 riders and is a transfer point for subway passengers and Long Island Rail Road commuters, along with drawing crowds at Barclays Center.

The upgrades are important for Brooklyn residents and visitors who depend on elevators to navigate the transit system, including people with disabilities, older adults and passengers with limited mobility. Replacing aging equipment can reduce repairs, limit service disruptions and make elevator service more dependable at a heavily used station.

The work included new elevator cabs and equipment, glass enclosures and street-level canopies, as well as modifications to the hoistways and pits. Mechanical and electrical systems in the machine rooms were modernized. Fire alarms, intercoms, cameras and remote monitoring equipment were upgraded to strengthen safety and help crews respond to outages.

Forte-Gramercy JV served as the design-builder, while Mid-American Elevator handled installation.

The MTA now has 164 fully accessible stations, including 49 made accessible since 2020.

Its 2025-2029 capital plan allocates nearly $7.1 billion for accessibility work, including plans to make 60 more stations accessible under the Americans with Disabilities Act and modernize 48 subway elevators.